Peak Evolution were awarded the contract to supplyand fit dimmable LED tape to walkways to achieve the desired LUX levels specified by NR. During the installation we upgraded mains cabinets to industry standards, installed new cable/containment routes alongside wiring control and supply feeds.
Duration
12 Weeks
Works Completed
Electrical, Mechanical
Project Features
Working under RTS as lead M+E roll.
Isolations and Rip Out within Operational Depot
Route Mapping and feasibility options.
Installation of Neon LED Tape
Installation of Schneider Distribution Boards
New Containment Systems
Sump Pump Installation
Test and Commission with LUX level Testing