Peak Evolution were awarded the contract to supplyand install a new external containment system with wiring for a 125amp 3 phase supply fitted with commando socket and switched fuse isolator. New circuit for 110v fixed transformer mounted on frame for industrial fan.
Duration
4 weeks
Works Completed
Design, Electrical
Project Features
Full Electrical Design Package.
Load Monitoring and Cable Routing Surveys.
Installation of Ladder Rack
Shut Down Works.110v Transformer
SWA install.
125amp 3 Phase Supply.
Test and Commission.