Peak Evolution were awarded the contract to fully fit out a new Pharmacy taking on the roles of Principle and Main Contractor. Following the initial site clearance we provided a full installation from a bare shell to provide, dispensary and sales areas, 2 consultation rooms, staff rest room, WC and storerooms.
Duration
10 weeks
Works Completed
Design, Joinery, Decoration, M&E, Flooring, Drylining and Ceilings
Project Features
Full design
Strip out of existing shop fittings
Supply and Installation of bespoke joinery items to suit required layout.
Full M&E package.
Decoration
Drylining and suspended ceiling installation
Lighting design and installation
Flooring
Store front replacement and footpath works
Principal Design and Main Contractor Roles